| Centennial Centre Expansion and new Aquatic Facility |
|
Annoucement Town of Gravenhurst and Gravenhurst YMCA Announcement December 16, 2011 The Town of Gravenhurst and YMCA are pleased to announce that the building will be open to the public on Monday, Dec 19th. All scheduled fitness classes and children’s programs will also be available. The pools remain under construction and more details will follow. We encourage the community to stay active over the holidays and come participate in our many programs. Winter/Spring Brochures & Registration will be available beginning Dec 19th. Happy Holidays!!!
On behalf of the Members of Council and Staff, it gives me great pleasure to welcome you to the website for our Project known as the Centennial Centre Expansion & new Aquatic Facility.
This website will keep residents and visitors updated on the progress of the Project. Council encourages you to visit this site regularly and share in the excitement as the design starts to take shape and the planning for construction begins. Watch our new facility take shape!
Please use the contact and comment opportunity to provide the Decision Committee with your comments.
Thank you.
For more updates and information on this important community project, please visit the links below.
Tenders Awarded to Date Project Documents and Information Building Committee Floor Plan Drawings - Ground Floor A, Ground Floor B, Second Floor A, Second Floor B Marshall & Murray Report - June 16th, 2011
September 2011 Phase II – Aquatic Facility
Landscape Tender - Fowler Construction - ongoing and expect to be completed mid October 2011. Skatepark Tender - New Line Skate Parks - site elevations completed and assembling equipment. Estimated completion by the end of October 2011. July 2011 Date for permanent power switch over will be on Monday March 7, 2011. Arena side is moving along on schedule, right now they are at approximately 90% complete for priming, painting is 30-40%, and tiling is at 60-70%. Pool Side - currently in construction for roofing above pools, 95% structural steel complete, exterior windows have been started. They are well underway to having enclosed by the end of March. Ice Season completed by - March 18th. Trailers (change rooms/washrooms) will be removed leaving one single washroom for Community Services staff. Dalton advises that they are still on schedule to have the arena side complete by Mid April, providing no hold ups on ordering./changes for products. Dalton will be booking the appropriate inspections as we near the completion of the arena side to have everything in place and ready for summer ice users. September/October/November 2010 Arena side - mechanical and electrical rough ins are in progress. - interior walls mostly up - roofing underway - windows beginning - exterior masonry has begun Pool side - foundations almost complete - floors being poured - ground floor walls underway - structural steel going up - 2nd floor core slabs - week of Nov. 22nd - timberwork will be started shortly (late week of Nov 22nd) - underground pipe completed
August 2010 July 2010 June 2010 May 2010 Reinforce existing arena structure Build temporary wall on east side of arena Demolition of dressing rooms and TFA Begin excavation of new dressing room areas Begin footings for dressing rooms March 2010 Remove arena stuff Asbestos abatement Disconnect services Locate all existing services on the property Build temporary wall on east side Mobilize welders for reinforcement of existing roof Mobilize demolition crew and fence
February 2010 - Pre-Qualification Package for sub trades and services posted on Town web site, Gravenhurst Banner and Daily Commercial News.
January 2010 - Decision Committee Terms of Reference approved.
December 2009 - Committee directs CS&P Architects to proceed to Design Development and Contract Documents.
December 15, 2009 - Report to Council summarizing public comments received at Public Open House on November 30, 2009. Please note a copy of the Report is available here! November 30, 2009 -A Stakeholders Meeting and a Public Open House were held in order for CS & P Architects to present the schematic design drawings to date. Also Dalton Company invited any trade vendors to submit their names to be put on list for construction suppliers. Public Comments were also received. October 20, 2009 – Simcoe Muskoka YMCA will be the provider of services for the new Aquatic Facility & Fitness Centre. Resolution passed at Committee of the Whole meeting.
Tenders Awarded To date are as follows: Demolition Tender - awarded to Greenspoon Specialty Contracting , Brampton, Ontario Arena Structural Reinforcing Tender - awarded to Paradise Steel Sprinkler Fire Protection Tender - awarded to Edwards Sprinkler, Barrie, Ontario Metal Decking Tender - awarded to Vixman Construction Ltd, Milton, Ontario Phase 1 Foundation - Reinforcing Steel - awarded to Salit Steel, Grimsby, Ontario Phase 1 Foundation - Concrete Formwork - awarded to Beehive Construction, Mississauga, Ontario Phase 1 Foundation - Supply of Concrete - awarded to Lafarge Concrete, Bracebridge, Ontario Phase 1 Foundation - Excavation & backfill - awarded to Corbett Wrecking, Dunnville + Coon Bros., Gravenhurst (fill only) Phase 1 Foundation - Masonry - awarded to Fox Masonry Corp Barrie, Ontario Structural Steel - was originally awarded to Nor Weld Orillia, but they could not meet deadlines, so the tender has now been awarded to Benson Steel. Survey work - T A Bunker, Gravenhurst, Ontario Tree Removal on site - Davey Tree Service, Orillia, Ontario Elevators - awarded to Schindler Elevator Corp, Scarborough, Ontario Below Grade Plumbing - awarded to Georgian Triangle Plumbing, Collingwood, Ontario Site Dewatering - awarded to Atlas Dewatering, Concord, Ontario Site Works - awarded to Arnott Construction, Midhurst, Ontario Shoring Tender - awarded to Anchor Shoring & Caissons Ltd - Toronto, Ontario Rebar - Part 2 Foundation - awarded to Salit Steel, Grimsby, Ontario Roof Top Unit (part) - pool dehumidification unit - awarded to HTS Egineering, North York, Ontario Masonry (Phase 2) - awarded to Fox Masonry, Barrie, Ontario Painting of Trusses - awarded to Inter-Provincial Ltd, Pickering, Ontario Electrical - Site & Ice Resurface room Lighting - awarded to Wallwin Electric, Barrie, Ontario Foundation (phase 2) - excavation & backfilling - awarded to Arnott Construction Phase 2 Foundation - Concrete Formwork - awarded to Chemello Contracting - Brampton, Ontario Press Steel -Screens & Hollow Metal Doors -awarded to Trillium Architectural Products - Toronto, Ontario Building Envelope Masonry - awarded to Squire Masonry Ltd - Cookstown, Ontario Placing & Finishing of Concrete - awarded to Marrick Floor Co Ltd Waterproofing - awarded to Aqua North - Ajax, Ontario Roofing & Metal Flashing - awarded to Blanchfield Roofing - North Bay, Ontario Mechanical - Main Building - Plumbing - awarded to Georgian Triangle Plumbing - Collingwood, Ontario Electrical - Main Building - awarded to Wallwin Electrical - Barrie, Ontario Curtain Wall, Aluminum Windows, Glass & Glazing - awarded to Barrie Metro Glass Under Pool slabs & sub drainage - Scope of Work - Georgian Triangle Plumbing - Collingwood, Ontario Overhead & Rolling Steel Doors - awarded to Northern's Own Garage Door Store - Orillia, Ontario Folding Panel Partitions - awarded to Extreme Partitions - Etobicoke, Ontario Gymnasium Equipment & Divider Curtain - awarded to Gymnasium & Health Equipment - Markham, Ontario Food Services Equipment - awarded to European Hotel & Restaurant Imports - Toronto, Ontario Pool Equipment - awarded to Acapulco Pools Ltd - Kitchener, Ontario Gym Wood floor & Group exercise sprung floor - scope of work - awarded to Barwood Flooring - Toronto, Ontario Spray Fireproofing & Intumescent Paint - scope of work - awarded to Firetherm Solutions Inc - Markham, Ontario Supply of Wood Doors - awarded to Commercial Doors & Hardware - Weston, Ontario Tender for Washroom Partitions - awarded to W.G. Wood Sales - Richmond Hill, Ontario Tender for all washroom accessories - awarded to W.G. Wood Sales - Richmond Hill, OntarioLandscape Tender was awarded to Fowler Construction, Bracebridge, Ontario. Skate Park Tender - awarded to New Line Skate Parks - British Columbia. Interior Cables/telephone lines - Bell Cabling Division - Huntsville, Ontario. Office Furnishings & Lobby Chairs - POI Business Interiors - Barrie, Ontario
Pre-Qualification Package - Information Letter - Form
June 2009 - Building Canada Fund Approval. Funding Partners: Government of Canada (Ministry of Energy & Infrastructure), Government of Ontario (Ministry of Agriculture, Food & Rural Affairs), Town of Gravenhurst. September 2009 - C S & P Architects named as the Lead Architects for the Project, Maureen O’Shaughnessy and Craig Goodman; Project Architects October 2009 - The Dalton Company named as the Construction Management Company October 2009 - Simcoe Muskoka YMCA named as the Service Provider (Operators) of the October 2009 - The Building Committee named as the Advisory Group providing input into October 2009 - The Building Committee’s Term of Reference approved.
November 2009 – Stakeholders Meeting and Public Open House held.
December 2009 - CS&P Architects directed to proceed to Design Development and contract
January 2010 - Decision Committee Terms of Reference approved.
February 2010 - Pre-qualification package for sub trades and services closes on February 10, 2010.
March 2010 - Demolition to Begin on Project
April 2010 - Reinforcement of existing arena, excavation and footings - change room
May 2010 - Foundation work - arena side, demo of Home Building Centre, excavation of pool side.
June 2010 - Site servicing, install dewatering system
July 2010 - Formwork pool side
August 2010 - Foundation work - pool side, masonry walls and steel erection - arena side
September 2010 - Council accepts in principal, an agreement with Simcoe Muskoka YMCA
June 2011 - Construction completed in Phase 1, Arena Side.
July 2011 - Phase 1 Occupancy permit received.
Government of Canada (Ministry of Energy & infrastructure),
Building Committee Members are: Environmental Committee Member Ralph Culham Accessibility Committee Member Judy Ring & Frank MacLaughlin as an alternate member Gravenhurst Children’s Place & Muskoka Family Focus Tanya Martin and Jennifer Purkis Seniors’ Centre Building Garnet Schenk Gravenhurst Minor Hockey Association Daniel Rolfe Simcoe Muskoka YMCA Representative David Grass Dalton Company Representatives Randy Dalton & Ravi Rajpal C S & P Architects Maureen O’Shaughnessy & Craig Goodman Town of Gravenhurst Council Members – Mayor John Klinck, Councilor Cairns, Town of Gravenhurst Staff Members – Manager of Development Services Nick Popovich,
A Decision Committee was formed, as per the Terms of Reference, and the members are as follows: Mayor Paisley Donaldson Councillor Rosemary King - Chair Davie Eidsness - Town of Gravenhurst - Chief Building Official Debbie Broderick - Town of Gravenhurst - Manager of Recreation, Community Services & Centennial Centre Operations Maureen O'Shaughnessy - CS&P Architects Craig Goodman - CS&P Architects Ravi Rajpal - Dalton Construction Co Len Beintema, Dalton Construction Co David Grass - YMCA Rick Larocque - Town of Gravenhurst - Centennial Centre Recreation Service Operator
Contact Debbie Broderick at (705) 687-6774, ext. 24 or This e-mail address is being protected from spambots. You need JavaScript enabled to view it
|
||||||||||||||||||||||||||||||||||||||
| Last Updated on Thursday, 02 February 2012 11:15 |